patent.fyi
Applications  /  US 2026/0365485
United States Patent Application Publication

US 2026/0365485 A1

Published
Nov 19, 2026
Filed
Dec 29, 2025
Earliest date on the face
May 15, 2025
Classification
B66B 19/00
First published here
Nov 23, 2026

Generated automatically. Not reviewed by a person. Not legal advice or an opinion.

Section 1 · machine-generated

What if?

Questions about how individual parts of claim 1 might be changed. A question may describe something different from what the claim language recites, or a version of it; no view is offered on which.

1.1Post-construction installation of reference fasteners

What ifWhat if reference fasteners are installed after the structural construction of the building finishes?
Claim language“during the construction of the building”

Once the concrete hoistway cures and floor slabs are complete, a laser scanner maps the full shaft geometry from bottom to top. Based on the point cloud, installers locate optimal plumb coordinates and drill mechanical expansion anchors into the finished shaft walls. This post-construction sequence compensates for structural column drift and slab pour tolerances.

1.1Approximate fastener placement with adjustable brackets

What ifWhat if fasteners are placed at approximate nominal intervals along the shaft wall without establishing a surveyed reference location?
Claim language“at a reference location”

Workers set anchor bolts along the hoistway walls at rough tape-measured floor intervals without precision surveying. Adjustable slotted mounting brackets with eccentric cam washers are bolted loosely to these anchors. A plumb-line laser beam is then projected down the shaft, and technicians slide and lock each bracket into exact vertical alignment before torquing the nuts.

Section 2 · machine-generated

Variations

Further arrangements of the same subject matter, described here as of the publication date at the foot of this page.

Other field of use

Pre-installed reference anchors for automated vertical warehouse lifts

In a multi-tier automated storage facility, steel anchor plates with machined datum holes are embedded into concrete rack columns during structural erection. These anchor plates establish fixed horizontal and vertical reference planes along the vertical lift shaft prior to equipment delivery. Modular vertical reciprocating conveyor masts and shuttle transfer frames are fabricated off-site with mating alignment pins and bolted directly onto the embedded plates. This arrangement transfers loads directly into the primary structure while eliminating on-site plumb-line surveying during lift assembly.

Parameter or scale variation

High-load multi-bolt reference brackets for heavy freight hoists

For heavy freight hoists rated between 10,000 kg and 25,000 kg, each reference location receives a four-bolt structural steel weldment rated for 120 kN shear load and 85 kN tension. Reference locations are spaced at vertical intervals of 1,500 mm along the hoistway wall, with horizontal position tolerances held within plus or minus 1.5 mm across a 60 m rise. Pre-assembled dual-rail carriage frames are hoisted into the shaft and secured to each four-bolt weldment using 24 mm diameter high-strength bolts tightened to 650 N·m. The closer vertical spacing and increased fastener capacity accommodate dynamic braking forces and eccentric pallet loading without supplemental shaft steelwork.

Specific version of a part

Laser-indexed cast-in anchor channel

A galvanized C-shaped steel anchor channel with welded headed studs is nailed to the inside face of the hoistway formwork before pouring. A rotating laser level aligns the channel centerline within 2 mm of the architectural shaft datum prior to concrete placement. After stripping the formwork, the exposed channel slot serves as both a structural anchor and a calibrated vertical reference.

Total-station guided expansion sleeve

During structural floor construction, a technician aims a robotic total station at a prism mounted on a rotary hammer drill to mark exact bracket coordinates on the cured concrete core. The technician drills a 16 mm bore to a 90 mm depth and sets a stainless steel torque-controlled expansion sleeve flush with the wall. A stamped metallic tag bolted to the sleeve records the measured offset from the master shaft plumb line.

Modular pre-wired hoistway rail cassettes

A factory fabricates 3-meter-long galvanized steel frame cassettes containing pre-aligned T-section guide rails, bracket standoffs, and bundled traveling cables. Each cassette includes precision-machined dowel pins at the top and bottom flanges to maintain rail-to-rail alignment across joints. Crated cassettes arrive at the building site sequentially by floor number and are hoisted into the shaft using a temporary top-floor jib.

Eccentric cam-bolt rail bracket assembly

An L-shaped hot-rolled steel rail bracket features an oversized slotted mounting hole that mates with the pre-installed wall fastener. An eccentric serrated washer and a high-tensile steel hex bolt pass through the slot, allowing 15 mm of lateral fine-tuning during rail plumbing. Once a feeler gauge confirms rail alignment, a pneumatic impact wrench torques the flange nut to 120 N·m to lock the serrated teeth.

On-site fabrication from raw steel stock

Bulk steel T-sections, flat bar stock, and unperforated plates are hoisted to a temporary site workshop adjacent to the hoistway. Technicians cut, mill, and drill the raw stock to match the measured shaft dimensions using portable machining tools. The resulting custom-sized rails and brackets are then moved directly into the shaft for mounting.

Cast-in-place anchor channel in concrete wall

A C-shaped galvanized steel anchor channel with welded T-headed studs is nailed to the interior face of the concrete formwork before pouring. Once the concrete cures and the formwork is stripped, the open channel slot sits flush with the hoistway wall at the surveyed floor elevation. The continuous slot provides a vertical reference datum and accepts T-head bolts at any lateral offset.

Section 3 · quoted from USPTO records

Other work

Passages reproduced word for word from two earlier-published U.S. patent documents, placed beside the language of claim 1. No characterization is offered. Each passage is marked A or B for the document it comes from; ¶ numbers are the paragraph numbers in the USPTO’s published full text of that document.

Document AUS 2024/0017965 A1
Published
Jan 18, 2024
Filed
Nov 10, 2021
Class
B66B 11/0005
Document BUS 12,024,403 B2
Published
Jul 2, 2024
Filed
Oct 22, 2020
Class
B66B 7/022
Claim 1
Document A
Document B
1.1installing a fastener at a reference location which provides a reference for the correct positioning of elevator components within the building, during the construction of the building;
1.2providing the elevator components; and
Similarly, connectors for hydraulic lines and/or electrical lines can be provided at, or protruding beyond, the respective top and/or bottom surfaces of the modular unit (e.g., pit module 100, shaft module 200, cap module 300) in which they are installed. Such operating components are installed during prefabrication of the modular units with sufficient precision to ensure proper engagement with a corresponding operating component in an adjacent modular unit.
A · US 2024/0017965 A1 · ¶ 68
1.3fastening the elevator components to the fastener.
The bracket can be clamped between two clamping plates of two fastening elements held between two nuts which are screwed onto the anchor bolts.
B · US 12,024,403 B2 · ¶ 16

An empty cell means only that no passage was reproduced there.

Why these two documents?

Only Document A has a passage for 1.2. Only Document B has a passage for 1.3. Both are classified in CPC B66B, as is this patent.

Additional background

Sentences reproduced word for word from these documents that state a problem, a purpose or benefit, a field of use, or an application or improvement.

Some have attempted to build the entire shaft offsite which is then shipped horizontally on a flatbed truck and then erected vertically as a single shaft which still creates many limitations.
A · US 2024/0017965 A1 · ¶ 4
So that the rail system can be constructed as straight as possible, the brackets are aligned in a plurality of axes during assembly.
B · US 12,024,403 B2 · ¶ 2
Cite aspatent.fyi, US 2026/0365485 A1, claim 1, first published 2026-11-23T00:46:45-05:00, https://patent.fyi/US20260365485/, SHA-256 f7c557b213d27c491e0ba2da8f6105044555ec6d87449a93b59a70c373d9436a
First published
Permanent addresshttps://patent.fyi/US20260365485/
Content fingerprint (SHA-256)f7c557b213d27c491e0ba2da8f6105044555ec6d87449a93b59a70c373d9436a
Methodv2026-11-18.2 · automated, not reviewed by a person
Correctionscorrections@patent.fyi